Former manufacturing facility, South Carolina
Western South Carolina, USA
Background
A now-closed manufacturing facility released significant PCE and TCE into unsaturated and saturated soil and groundwater.
Technology Used
EZVI injection combined with anaerobic bioremediation
Approach
EZVI was injected to drive dechlorination directly in the source area, supported by ongoing anaerobic biological activity.
Results
- Source-area groundwater CVOCs decreased approximately 20% overall after 18 months, with ~50% average removal in three monitoring wells
- A further 6 months of treatment reduced soil CVOC concentrations by over 90% with no rebound